February 11, 2008

Deployment (Merged)

11 February 2008

The two modules of E-Pasa (E-Portfolio and E-Assess) are now merged. Here’s the link:

http://121.97.188.109:8081/ePasa/Home.html

Joseph Fabila
Ma. Eden Ramirez
(E-Portfolio)

Joebet Isaac V. del Rosario
Francis Hans E. Mohan
(E-Assess)

February 1, 2008

Ontology Engineering 2

The image above represents something like a snap shot of the ontology model based on the scheduling ontology file I created. This scheduling ontology is based on the domain theory by Axel van Lamsweerde. During the process of coming up with acceptable meeting schedule(s)/date(s), the ontology model, which can also be considered the “brain” of an agent, contains a Meeting instance, and several (at least one) instances of Participant. Before continuing, I’d like to note that the image does not illustrate all the components of the ontology I created. All of the components in the illustration are only those that I find necessary to describe the overview of the operation I’d like to do with the ontology model. (Although it raises a question on why do I actually put the other components if they are not necessary. But I’d like to leave the model as I’ve created it for the moment.)

February 1, 2008

Implementation Log 9

Module: Ontology/Scheduling

Summary:

  • Created Scheduling ontology that provides a basis for modeling the scheduling process.
  • Conducted hands on on Jena by creating an in-memory model based on the ontology created.
  • Created test individuals to form a sample knowledge base.

Keep reading →

January 31, 2008

Progress

January 31, 2008
Joebet Isaac V. del Rosario
Francis Hans E. Mohan

The following functionalities have been implemented and deployed:

1. Assess Submission

2. View Statistics (partial)

January 30, 2008

ePasa Progress Report

January 30, 2008

Eden Ramirez & Joseph Fabila

As of now, we are almost finished coding our part of the project. The only functionality we are finishing is the Rate Public Work for public viewers. After finishing that functionality, we are on to merging our part of the project with the Assessment Group and hopefully, after that, there would be minimal rework and we could start the testing of the whole project.

By next week, we could upload the updated documents.